Development Timeline Of Goldcrest

July 2018

Amazing progress seen at Goldcrest just before July, On ground and lower ground Alfatah store is doing the finishing work for its store and on 5th , 6th and 7th floor apartment walls and structure is being constructed with full pace.

 

March 2018

Finishing has been started on front elevation, parking areas and basements. Model apartment will be ready soon.

 

Feb 2018

Grey structure for 8 stories is complete and the work is in progress day and night. The 9 floor is 30% complete and in progress.

Jan 2018

Grey structure for 7 stories is complete and the work is in progress day and night.

Grab yours before its too late
Invest in the first Mall of DHA Lahore
Book Now
Goldcrest Mall DHA Lahore
Book Now
Grab your shop before its too late
MAKE A WISH BEFORE YOU LEAVE
YOUR WISH IS OUR COMMAND. GIVE OUR GENIE A CHANCE
MAKE MY WISH COME TRUE
MAKE A WISH BEFORE YOU LEAVE GIVE OUR GENIE A CHANCE
MAKE MY WISH COME TRUE
LET US DO THE HARD WORK SO YOU DO NOT HAVE TO
Join the luxury of our managed real estate services to find out when, where and how to invest .
APPLY NOW FOR OUR SOLUTION
What are your goals?
Your destination?
Capital Gains
Rental Returns
Pakistan
Dubai
Let us do the hard work so you do not have to
Join the luxury of our managed real estate services to find out when, where and how to invest .
APPLY NOW FOR OUR SOLUTION
Rental Returns
Pakistan
Capital Gains
Dubai
Your goals?
Your destination?
Get access to the real information, subscribe our BLOG
Subscribe Now!
No spam ever, unsubscribe anytime.