Development Timeline Of Indigo Heights
Jan 2018
Grey structure for 3 Basements, LG, Ground and first 8 floors is complete.The construction is ahead of required time limit.
Nov 2017
Grey structure for 3 Basements, LG, Ground and first 4 floors is complete. Commercial area grey structure is completed now and the work is being done very speedily.
August 2017
Construction work on 1st and 2nd floor in progress.
June 2017
Ground floor is finished and now construction is moving on to first floor.
Apr 2017
Work on basements is almost complete and we are finally on the ground level.
Feb 2017
After completion of digging, speedy construction in progress on the 3 basements.
Dec 2016
Digging completed in December and construction work begins for the 3 parkings.
Nov 2016
Digging continues in November 2016 for 3 basements.